Scene 3 / 11 08:30 WITA — Ir. Sudarto (Mine Planner) · Klik tombol "Generate" → Foxel membuat rencana harian otomatis dari rencana mingguan W17. Match blok × excavator × DT × operator × target. 08:30 WITA — Mr. Sudarto (Mine Planner) · Click "Generate" → Foxel builds today's plan from Weekly W17. Matches block × excavator × haul truck × operator × target.

Rencana Harian · Selasa 22 April 2025 Daily Plan · Tuesday 22 April 2025

Generated dari Rencana Mingguan W17 · 3 shift · Pit North + Pit South Generated from Weekly Plan W17 · 3 shifts · Pit North + Pit South

Foxel generated · 08:28 WITA Foxel generated · 08:28 WITA
Target Hari Ini
5.667 ton
pro-rata dari Rencana Mingguan
OB Removal
27.200 BCM
SR 4,80
Blok Aktif
5
3 di North · 2 di South 3 in North · 2 in South
Unit Deploy
4 ex · 7 DT
EX-04 breakdown, cover oleh EX-05 EX-04 down, backfilled by EX-05
Operator On-duty
127
43 pagi · 42 siang · 42 malam 43 morning · 42 afternoon · 42 night

Timeline 24 Jam · Shift Allocation 24-Hour Timeline · Shift Allocation

Shift Pagi 07-15 · Shift Siang 15-23 · Shift Malam 23-07 Morning 07-15 · Afternoon 15-23 · Night 23-07

Pagi Siang Malam OB
Unit · Operator
00
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
23
EX-01
Wahyudi R.
PC2000 · Pama
PN-B2-02 · 850 t
PN-B2-02 · 920 t
PN-B2-02 · 900 t
EX-02
Sutrisno H.
PC2000 · Pama
PN-B3-01 OB · 3.800 BCM
PN-B3-01 OB · 4.200 BCM
PN-B3-01 OB · 4.000 BCM
EX-03
Hadi P.
EX1200 · KTS
PS-B1-02 · 540 t
PS-B1-02 · 620 t
PS-B1-02 · 600 t
EX-04
BREAKDOWNBREAKDOWN
ETA 3 hariETA 3 days
Maintenance · Hydraulic Pump Maintenance · Hydraulic Pump
EX-05
Joko M.
CAT 374F · KTS
PS-B2-01 · 420 t
PS-B2-01 · 460 t (+cover EX-04)
PS-B2-01 · 450 t
DR-01
Kurniawan D.
Atlas Copco · Pama
Drilling PN-B4-01 · 28 hole Drilling PN-B4-01 · 28 holes

Penugasan Armada — Shift Pagi (Aktif Sekarang) Fleet Assignments — Morning Shift (Active Now)

Shift Excavator Operator Blok DT Pool Target Ton BCM
M EX-01 Wahyudi R. PN-B2-02 DT-001, 002, 003 920 4.800
M EX-02 Sutrisno H. PN-B3-01 (OB) DT-005, 006 - 4.200
M EX-03 Hadi P. PS-B1-02 DT-007 620 2.800
M EX-05 Joko M. PS-B2-01 DT-005 (shared) 460 1.900
M DR-01 Kurniawan D. PN-B4-01 (dev) - - 28 hole 28 holes
TOTAL SHIFT PAGI 2.000 13.700

K3 Briefing — Shift Pagi HSE Briefing — Morning Shift

Auto-generated dari Hazard Register + cuaca BMKG Auto-generated from Hazard Register + BMKG weather

JSA siap

Hujan Sore (probabilitas 65%) Afternoon rain (65% probability)

BMKG: hujan lebat 14:00-17:00. Haul road PN-B3 tanjakan curam, potensi licin. Siapkan grader + water truck stand-by. BMKG: heavy rain 14:00-17:00. PN-B3 haul road has steep grade, slip risk. Keep grader + water truck on standby.
Grader Rain control

Crossing jalan akses PS-B1 dan PS-B2 Access-road crossing at PS-B1 / PS-B2

DT-007 dari B1 crossing dengan EX-05 di B2. Spotter wajib di intersection 08:00-12:00. DT-007 from B1 crosses EX-05 at B2. Spotter mandatory at the intersection 08:00-12:00.
Spotter Radio check

Blast Drill PN-B4-01 Blast drilling at PN-B4-01

28 hole, ANFO 420 kg. Drilling DR-01 09:00-14:00, blasting dijadwalkan Kamis 24/4. 28 holes, 420 kg ANFO. Drilling by DR-01 09:00-14:00; blast scheduled Thursday 24/4.
Blaster cert POLRI permit
Helm SNI Safety shoes Rompi reflektif Ear plug Masker debu Kacamata safety

Rencana Harian siap dikirim ke KTT Daily plan ready to send to KTT

Estimasi notifikasi diterima Pak Budi: < 10 detik. KTT dapat approve 1-tap dari mobile di pit. Estimated notification to Mr. Budi: < 10 seconds. KTT can approve with one tap from his mobile on the pit.

Kirim ke KTT Send to KTT
Rencana Mingguan 3 / 11 KTT Mobile Approval → KTT Mobile Approval →