Scene 3 / 7 09:00 WITA — Selasa, 5 Mei 2026 · SR variance April +8,3% melebihi ambang PP 96/2021 (max 5%). Trigger otomatis: revisi RKAB mid-year wajib. Foxel identifikasi 3 bab harus di-update (produksi, OB, biaya). Ibu Ratih + Ir. Sudarto + konsultan Mineserv kolaborasi, submit ke ESDM sebelum 25/5. 09:00 WITA — Tuesday, 5 May 2026 · April SR variance +8.3% exceeds PP 96/2021 threshold (max 5%). Auto-trigger: RKAB mid-year revision required. Foxel flagged 3 chapters for update (production, OB, cost). Mrs. Ratih + Mr. Sudarto + consultant Mineserv collaborate, submit to ESDM before 25/5.
RKAB Revisi Mid-Year · Trigger SR Variance +8,3%
Approved RKAB B-342/2025 · PP 96/2021 tolerance 5% · deadline 25/5/2026
Ibu Ratih + Ir. Sudarto
Compliance + Mine Planner
PP 96/2021 TRIGGER

Variance SR +8,3% — revisi RKAB mid-year WAJIB sebelum 25 Mei 2026SR Variance +8.3% — RKAB mid-year revision REQUIRED before 25 May 2026

PP 96/2021 pasal 47 mensyaratkan revisi RKAB jika realisasi menyimpang >5% dari plan. Jika tidak dilakukan: ESDM bisa tolak laporan bulanan + denda administratif IDR 500jt. Foxel auto-trigger workflow revisi saat variance terdeteksi.PP 96/2021 Article 47 requires RKAB revision if realisation deviates >5% from plan. Without it: ESDM may reject monthly reports + IDR 500M administrative fine. Foxel auto-triggered the revision workflow when the variance was detected.

SR Plan
4,80 BCM/t
SR Actual YTD
5,20 BCM/t
Deviasi
+8,3%
Deadline revisi
25/5/2026

Perbandingan RKAB Plan vs Actual YTDRKAB Plan vs YTD Actual

ParameterRKAB Plan 2026YTD Actual (Apr)DiffRevisi ke
ROM Production (t)2.000.000612.000 (4 bln)+2,0%2.040.000
Overburden (BCM)9.600.0003.182.400 (4 bln)+8,3%10.400.000
SR (BCM/t)4,805,20+8,3%5,10 (revised)
Revenue (USD)164.000.00045.900.000 (28%)+1,2%166.000.000
Cost OPEX (IDR)1.850.000.000.000620.500.000.000+5,8%1.957.000.000.000
Manpower KTS+Contractor650668+2,8%670
Reklamasi target (ha)4512on-track45 (sama)
K3 LTIFR0,800,60-25%0,65 (better)
Akar penyebab variance (dari M1 variance scene):Variance root cause (from M1 variance scene): Geologi Pit North bench 3 lebih keras dari model JORC, butuh lebih banyak blast + drilling. SR naik karena OB ekstra. Produksi ROM stabil (bahkan +2%) karena equipment efficiency naik. Pit North bench 3 geology harder than the JORC model — more blasting + drilling required. SR rose from extra OB. ROM production stable (actually +2%) due to equipment efficiency gains.

3 Bab Harus Revisi3 Chapters Require Revision

Bab 2 · Produksi & OBCh. 2 · Production & OBEditEdit
ROM revised 2.040k t (+40k) · OB revised 10.400k BCM (+800k) · SR revised 5,10 BCM/t. Narasi: Pit N-B3 geologi lebih keras.ROM revised 2,040k t (+40k) · OB revised 10,400k BCM (+800k) · SR revised 5.10 BCM/t. Narrative: Pit N-B3 harder geology.
Bab 5 · Biaya OperasionalCh. 5 · Operating CostEditEdit
OPEX naik IDR 107 miliar (+5,8%) karena ekstra drilling + ANFO + diesel fleet. Sudah tercover oleh revenue naik.OPEX rises IDR 107 B (+5.8%) from extra drilling + ANFO + fleet diesel. Offset by higher revenue.
Bab 8 · ManpowerCh. 8 · ManpowerEditEdit
Tambah 20 orang (18 kontraktor Pama + 2 KTS) untuk handle OB ekstra. Gaji +IDR 2,8 M/bulan.Add 20 people (18 Pama contractor + 2 KTS) for extra OB. Payroll +IDR 2.8 B/month.
Bab 1, 3, 4, 6, 7, 9Ch. 1, 3, 4, 6, 7, 9Tidak perluNo change
Ringkasan exec, eksplorasi, kualitas, penjualan, K3, reklamasi — sesuai plan.Exec summary, exploration, quality, sales, K3, reclamation — on plan.

Flow Submit ESDMESDM Submit Flow

Auto-trigger + draftAuto-trigger + draft
5/5 08:30 · Foxel detect variance
done
2
Review internal (hari ini)Internal review (today)
Ratih + Sudarto + Budi
5/5
3
Konsultan Mineserv reviewMineserv consultant review
validasi metodologi + signaturemethodology validation + signature
10/5
4
Board approval (Ir. Hendra)Board approval (Ir. Hendra)
President Director BSrE
15/5
5
Submit e-RKAB portalSubmit e-RKAB portal
ESDM evaluasi 7 hari7-day ESDM evaluation
25/5
On-track: deadline 25/5 WILL be met · 20 hari buffer On-track: 25/5 deadline WILL be met · 20-day buffer